Our New Home

Building a new home

Sunday, 29 July 2012

Roof Gables and Doors

Gables



Front Door





Interior Glazed Doors







Posted by Nathan and Dayna at 8:33:00 pm 1 comment:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Wednesday, 18 July 2012

Eaves and Gyprock...





Posted by Nathan and Dayna at 8:08:00 pm No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Friday, 6 July 2012

Bricks and Roof Complete!

The brickwork and the roofing have now been completed.




Brickwork took a while due to various issues, but the end result looks really good.
Posted by Nathan and Dayna at 5:03:00 pm No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest

Sunday, 1 July 2012

Brickwork and roof nearly complete...



Posted by Nathan and Dayna at 6:37:00 pm No comments:
Email ThisBlogThis!Share to XShare to FacebookShare to Pinterest
Newer Posts Older Posts Home
Subscribe to: Posts (Atom)

About Me

Nathan and Dayna
View my complete profile

Progress Dates

  • 10/9/2012 Fit out starts
  • 20/8/2012 Painting starts
  • 4/8/2012 Tiling starts
  • 2/8/2012 Fence removed and a site clean up
  • 30/7/2012 Kitchen cupboards and bases installed
  • 23/7/2012 Interior Carpenters start
  • 18/7/2012 Gyprock
  • 13/7/2012 Eaves
  • 6/7/2012 Brickwork Finished
  • 3/7/2012 Electrical Rough In
  • 3/7/2012 Roof complete
  • 28/6/2012 Roofing starts
  • 31/5/2012 Brickwork starts
  • 9/5/2012 Framework complete
  • 13/4/2012 Framing begins
  • 23/3/2012 Framework delivered
  • 19/3/2012 Slab Poured
  • 12/3/2012 Waffle Pods
  • 27/2/2012 Some trenching and pods delivered
  • 24/2/2012 Piers
  • 23/2/2012 Formwork starts
  • 21/2/2012 Temporary fencing
  • 20/2/2012 Site cut
  • 10/2/2012 Pegs placed
  • 31/1/2012 Job placed on the construction list
  • 31/1/2012 Letter to commence received by builder
  • 11/1/2012 Comply and Development Authority received
  • 23/12/2011 Electricals signed
  • 12/12/2011 File sent for Comply and Development
  • 29/11/2011 Contracts signed
  • 26/9/2011 Acceptance of tender
  • 26/9/2011 Colour Selections
  • 1/7/2011 Deposit Paid

Followers

Blog Archive

  • ▼  2012 (25)
    • ►  September (1)
    • ►  August (3)
    • ▼  July (4)
      • Roof Gables and Doors
      • Eaves and Gyprock...
      • Bricks and Roof Complete!
      • Brickwork and roof nearly complete...
    • ►  June (3)
    • ►  May (2)
    • ►  April (1)
    • ►  March (6)
    • ►  February (5)
Picture Window theme. Theme images by TommyIX. Powered by Blogger.