Friday 14 September 2012

Saturday 4 August 2012

Kitchen

The Kitchen cupboards and bases were installed on Monday. The Laundry cupboards and sink also went in and  the bathroom vanities have all been delivered.


Friday 6 July 2012

Bricks and Roof Complete!

The brickwork and the roofing have now been completed.




Brickwork took a while due to various issues, but the end result looks really good.

Saturday 2 June 2012

Brickwork starts!

The brickies have started...


Back of Garage


Front of Garage


Master Bedroom


Saturday 12 May 2012

Framework Complete

The framework stage is now complete, including gutters and facias...




The bricks have been delivered...


Tuesday 1 May 2012

Again??

This time it was the crane that got bogged on our block. Due to the fact that the builder hadn't repaired the driveway the crane driver decided it would be a good idea to try and carry the rest of the framework up to the house site by going off the driveway this is the result...



Finally the driveway has had a temporary repair...



Plumbing trenches around the house have been dug and have had all the pipes layed...




Windows have been delivered...





Saturday 14 April 2012

Frames

The framing starts to go up...




And by the end of the day...


Most of the wall framing is up.

Tuesday 27 March 2012

Framework Arrives


The steel framework was delivered to the block late last week.






The trenches for the water, power and telstra have all been dug.